Network Provisioning Intervals
-- Each ILEC shall provide essential facilities and services that comply with
the following installation intervals:
a.
Network Elements -- Each ILEC shall provision essential network facilities and
services in accordance with the following intervals and shall measure
provisioning intervals for each of the following loop facilities and services
as described in
R746-365-5 -(C)(3)(c).
(i) Unbundled Loops -- Provisioning intervals
for an unbundled loop will vary by circuit and facility type, the number of
loops requested on a service order, availability of facilities and whether or
not a dispatch of ILEC personnel must occur. The following essential facilities
will be provisioned for telecommunications corporations within the specified
intervals.
|
TABLE
|
|
Facility Type
|
Quantity
|
Interval
|
|
DSO or analog equivalent, dispatch, facilities
available:
|
1 - 24
|
5 days
|
|
24 - n
|
negotiated
|
|
DSO or voice grade equivalent, no
dispatch:
|
1 - 24
|
3 days
|
|
24 - n
|
7-10 days
|
|
DS1 -- Facilities provisioned and
available:
|
|
5 days
|
|
ISDN -- Facilities provisioned and
available:
|
|
7 days
|
|
XDSL -- Facilities provisioned and
available:
|
|
7 days
|
|
DS3 -- Facilities provisioned and
available:
|
|
7 days
|
|
OC3 -- Facilities provisioned and
available:
|
|
15 days
|
|
OC4 - Higher -- Facilities provisioned and
available:
|
|
15 days or negotiated due date.
|
b. Wholesale Services -- Installation
intervals for wholesale services shall vary depending upon whether an existing
end user service provided by an ILEC is transferred to another
telecommunications corporation, or, is a new service installation.
(i) An ILEC shall transfer wholesale services
without changes for an existing end user served by the ILEC within one business
day following receipt of a service order from the telecommunications
corporation.
(ii) An ILEC shall
transfer wholesale service with changes for an existing end user served by the
ILEC within three business days following receipt of a service order from the
telecommunications corporation.
(iii) An ILEC shall install new wholesale
service to a new end user, if facilities are available, within three days
following receipt of a service order from the telecommunications
corporation.
c.
Collocation -- The following provisioning intervals and optional arrangements
are common to both virtual and physical collocation:
(i) Upon receipt by an ILEC of a request for
collocation, the ILEC shall within 15 days notify the telecommunications
corporation whether sufficient space exists. If the telecommunications
corporation disputes an ILECs denial of a request for collocation, and the
carriers cannot negotiate a mutually satisfactory resolution, the
telecommunications corporation may petition the Commission pursuant to Section
54-8b-17 for an expedited hearing
and resolution of the dispute. The burden shall be on the ILEC to demonstrate
to the Commission that collocation is not practical due to space limitations or
is technically infeasible.
(ii) If
collocation is available, the ILEC shall within 25 days following receipt of a
request for collocation provide a written quotation containing all
non-recurring charges for construction of the telecommunications corporation's
requested collocation arrangement.
(iii) The telecommunications corporation
shall within 30 days following receipt of the ILEC's quotation, by written
notice to the ILEC:
1) accept the quotation;
2) withdraw the request for
collocation; or,
3) provide the
ILEC an independent contractor quotation for construction of the requested
collocation arrangement.
(iv) If the telecommunication corporation
accepts the quotation from the ILEC, collocation equipment shall be installed
on the ILEC's premises in accordance with the following provisioning intervals:
1) For physical collocation arrangements, the
ILEC shall within 45 days of the telecommunication corporation's acceptance of
the ILEC's quotation complete construction of the collocation space necessary
and sufficient for installation of the CLEC's collocated interconnection
facilities. The ILEC shall grant the telecommunications corporation access to
the collocation space to install network elements therein.
2) For virtual collocation arrangements, the
ILEC shall within 45 days after delivery of the telecommunication corporation's
collocation equipment complete provisioning of all network facilities ordered
by the telecommunications corporation.
(v) If the telecommunication corporation
provides the ILEC an independent contractor quotation for construction
associated with a collocation arrangement, the ILEC shall within 15 days of
receipt of the quotation:
1) accept the
proposal and grant to the independent contractor access to the ILEC's premises
to complete construction of the collocation space and installation of the
collocated interconnection facilities;
2) amend the ILEC's own quotation to perform
on substantially similar terms, including, without limitation, price, the
services specified in the independent contractor's quotation. If the
telecommunication corporation accepts the ILEC's amended quotation,
construction of the collocation space shall proceed as described in
R746-365-4(B)(3)(c)(iv);
or,
3) reject the proposal. If the
ILEC refuses to accept an independent contractor quotation or amend its own
quotation, the telecommunications corporation may petition the Commission for
an expedited hearing and resolution of the dispute pursuant to
R746-365-8(B).